Tuesday, October 27, 2009

Day 26 - 10/27

Not a lot to report today, I was here for the heating rough-in inspection.  Once complete, framing was placed around the heating stack for the second floor here in the first floor closet.
With everything in that closet we reduced the opening from 5 feet to 4 feet as well.


The bit of wall left to demo (at the end of the old hall) was also removed.  leaving the nice big opening that we'll have on the way into the dining room.  The marks on the floor are where the old wall used to be.  It made a corner and went into the blue bedroom.


And the downstairs bathroom fan was vented out the back of the house.  It's there just above the glass block window.